LOD 300, 400 or 500: what should you actually specify?
Specifying the wrong level of development is one of the most common and costly mistakes in BIM briefs.
LOD 300 describes elements with accurate size, shape, location and orientation, which suits design coordination. LOD 400 adds fabrication and assembly detail, which suits shop drawings and installation. LOD 500 reflects the verified as-built condition and is used for handover and facility management.
Ask three questions before you write the brief. What decision will this model support? Who will use it next? And at which stage does that person need it? Modelling everything at LOD 400 early wastes budget, while modelling too little blocks coordination.
A good rule: specify the level per element and per stage, not per project, and write it into the BIM execution plan so every discipline works to the same table.